Brief · AI Infrastructure
Nebius contracts substation for a second 70 MW Mäntsälä building
What happened
Caverion announced an approximately €15 million contract to design and deliver a substation for a second 70 MW Nebius data-centre building in Mäntsälä. The contract is project evidence, not proof that the building is permitted, under construction, energized or operational. [4]
- Updated
- Sources
- 5
- Sections
- 5
- Method
- Source-backed analysis
Why it matters
The contract advances the future phase beyond a capacity proposition by identifying a contractor, electrical asset, contract value and target period. It does not turn the existing 75 MW-connected site into a currently operating 145 MW campus.
Key evidence
- Nivos identifies the existing operating-site connection as 75 MW. [1]
- The existing expansion entered use in November 2025 and February 2026. [1][2]
- Caverion reports an approximately €15 million substation contract for a second 70 MW building. [4]
- Autumn 2027 is a contractor target for substation completion, not an evidenced energization or operation date. [4]
Current state
Existing facility — OPERATIONAL. A 75 MW grid connection is evidenced; exact active IT load is undisclosed. [1][3]
Second building — ANNOUNCED / GRID INFRASTRUCTURE CONTRACTED. A 70 MW company claim and substation contract are evidenced. [4]
Combined 145 MW — CONTINGENT INTERPRETATION. It is an arithmetic future footprint only if the second building is delivered, not current operating capacity.
What remains unknown
Whether a final building permit for the second 70 MW building has been granted. The reviewed municipal-document monitor found no matched decision, but its coverage is not exhaustive. [5]
Whether construction of the second building has begun.
The contracted grid basis and energization date for the second building.
The site-specific active IT load of the existing facility and any future phase.
Whether the autumn 2027 substation target will be met; it is a schedule, not a completed milestone.
Source roles
Original / primary evidence: S06, S07, S08 and S10. These establish the existing connection and commissioning sequence, company completion context, power-category boundary and the new substation contract.
Secondary supporting source: S11. It provides bounded municipal-document search context and is not proof that no permit exists.
- Version
- v1.0
- Evidence cutoff
Limitations
- The substation contract is evidence of procurement and intended electrical infrastructure, not proof of building completion or grid energization. The 70 MW description is a future building claim and must not be combined with the existing 75 MW connection as current capacity.
Known unknowns
- Final public permit and construction-start state for the second building, contracted grid basis, energization date, and any schedule revision after the 2 November 2026 evidence cutoff remain unknown.