Intel Report · AI Infrastructure

Nebius Mäntsälä: 75 MW grid connection, 70 MW planned

Nebius’s Mäntsälä facility is operating with a 75 MW grid connection. A separate 70 MW building has contracted substation delivery, but its permit, construction, energization and active IT load remain unestablished.

Edward TrubinPrincipalPublished November 2, 202612 min
Updated
2 Nov 2026 · 00:00 UTC
Sources
13
Sections
12
Method
Source-backed analysis
Methodology →Corrections →

In this analysis

The research questionFrom expansion claim to physical evidenceCommissioning established the current stateThe material change: a second 70 MW buildingCapacity reconciliationProject timelineOrganizations and evidence rolesWhat remains unknownResearch conclusion and limitationsSource roles

Thesis

The reviewed evidence supports an operational Mäntsälä facility with a 75 MW grid connection and a completed two-stage expansion. It separately supports a substation contract for a future 70 MW building. Those states must not be collapsed into a claim that 145 MW is currently operational.

Key findings

  1. Nivos identifies the enlarged operating-site electricity connection as 75 MW and reports that the expansion entered use in November 2025 and February 2026. [S06]
  2. The exact site-specific active IT load remains unknown; Nebius distinguishes connected and active power, and its disclosed active-power figure is global. [S08]
  3. Caverion’s October 2026 contract advances a second 70 MW building to contracted substation delivery, but does not establish a permit, construction start, energization or operation. [S10][S11]
  4. A 145 MW figure is contingent arithmetic, not current capacity; MW/MVA and building-count conflicts remain explicitly unresolved. [S04][S05][S06][S10][S12]

The research question

Nebius’s Mäntsälä data centre is often described through a single capacity number. That is convenient, but it obscures the physical sequence behind the number and creates a material risk of mixing an operating site with a future expansion.

The reviewed evidence supports a clear current state. Mäntsälä is an operational data-centre site with a 75 MW grid connection. Its latest completed expansion entered use in two phases, in November 2025 and February 2026. A separate second building, described as 70 MW, now has a contracted substation delivery. That later contract is meaningful project evidence, but it does not establish that the second building is permitted, under construction, energized or operational. [S06][S07][S10]

Fact — a 75 MW connection and phased commissioning are evidenced for the existing site. [S06]

Company claim — a second 70 MW building is planned alongside it. [S10]

Interpretation — 145 MW is a contingent future arithmetic footprint, not current physical capacity.

Unknown — the exact active IT load at Mäntsälä and the permit, construction and energization states of the second building.

That separation matters because an announced megawatt is not one uniform thing. It can describe a corporate target, a grid agreement, a permitted building, a connected facility, an active IT load or a future phase. The public record for Mäntsälä contains several of those categories. It does not make them interchangeable.

From expansion claim to physical evidence

Nebius announced on 8 October 2024 that it would triple capacity at Mäntsälä to 75 MW. The company also described an ambition to deploy up to 60,000 GPUs. Those were company claims about a planned expansion, not completion evidence at the date of announcement. [S01]

The same day, local energy and grid organization Nivos disclosed an earlier physical dependency. Nivos and Global DC Oy had signed an enlarged grid-connection agreement in June 2024, and the expansion was expected to include two new server halls. [S03] This moved the evidence beyond a standalone company target: a named local network counterpart had entered an agreement tied to additional electricity transmission. It still did not prove that the new halls existed or that the enlarged connection was live.

Planning evidence followed. On 11 December 2024, Mäntsälä’s municipal development board approved building permit LP-505-2024-00480. The decision covered an approximately 20,000-square-metre expansion comprising a new data-centre building and a limited expansion of the existing energy-transfer building. The authority also found the application consistent with the zoning plan. [S04] The permit is strong evidence of an authorized physical scope. It does not itself provide a megawatt figure and does not prove later construction or commissioning.

The distinction between permit and delivery is visible in the subsequent record. Nivos’s retrospective project account says ground works started in January 2025 and technical installations followed in April and May. [S06] Caverion separately disclosed an approximately €80 million delivery scope covering cooling, heat recovery, ventilation, fire systems and electrical and HVAC work. It described an extension to the existing building and two new data-centre buildings, with a target total capacity of 75 MW. [S05] That physical-scope description does not exactly match the municipal permit’s one new data-centre building plus energy-transfer-building expansion. [S04] The reviewed evidence does not establish whether the difference reflects terminology, phasing or a changed scope, so the discrepancy is preserved. Both records nevertheless support active construction and technical delivery, while their scheduled completion language remained forward-looking when published.

Commissioning established the current state

The strongest completion evidence comes from Nivos’s 31 March 2026 account. It states that the first half of the expansion entered use in November 2025 and the second half in February 2026. The same source identifies the enlarged connection as 75 MW. [S06] Nebius, in a separate company announcement on the same date, said that the Mäntsälä expansion to 75 MW had been completed earlier in 2026. [S07]

Taken together, these sources support an operational state for the completed expansion. The utility record supplies the connection basis and phased dates; the operator supplies a completion statement. The evidence is stronger than an announcement or contractor schedule because it describes parts of the facility entering use.

It remains important to state exactly what the 75 MW represents. Nivos calls it a connection. That does not mean all 75 MW is continuously consumed, devoted to IT equipment or available as active compute load. Nebius’s own reporting definitions distinguish contracted power, connected power and active power. Its annual filing gives a 170 MW active-power figure at portfolio level, not for Mäntsälä specifically. [S08] Assigning that portfolio number—or any inferred share—to this site would be unsupported.

Nivos also reports an operator statement that the facility has approximately 40 MW of liquid-cooled capacity. [S06] That is useful technical context, but its basis differs from the 75 MW connection. It should not be treated as an independently verified active IT-load figure. The strongest defensible wording is therefore: the existing Mäntsälä facility is operational with a 75 MW grid connection; exact site-specific active IT load is not publicly established in the reviewed evidence.

The material change: a second 70 MW building

On 2 October 2026, Caverion announced a new contract worth approximately €15 million to deliver a substation for a second 70 MW data-centre building at Mäntsälä. The contractor described this building as being alongside the existing 75 MW data centre and targeted substation completion for autumn 2027. [S10]

This is a material project change. A named delivery contractor, contract value, electrical asset and target period now exist in the public record. The second phase has moved beyond an abstract campus aspiration into contracted grid-infrastructure delivery.

But the new evidence has a precise limit. A substation contract is not a building permit. It is not proof that construction of the data-centre building has started. Its delivery target is not an energization date, and none of these items establishes active compute capacity. The reviewed secondary municipal-document monitor tracks the separate 70 MW project but reports no matched municipal decisions in its search set. [S11] That negative search is useful for directing further work, not for proving that no permit exists; the monitor’s coverage is not exhaustive.

The correct state for the future phase is therefore announced / grid infrastructure contracted, with permit, construction and energization unresolved. Calling the whole campus 145 MW today would collapse two different evidence states into one number.

Capacity reconciliation

75 MW — existing enlarged grid connection; completed expansion in use by February 2026. [S06][S07] It does not establish continuous utilization, active IT load or GPU load.

Approximately 40 MW — liquid-cooled capacity attributed to the site director. [S06] It is not an independently verified total active IT-power figure.

70 MW — company/contractor description of a second future building with a substation contract. [S10] It does not establish current connection, completion, energization or operation.

145 MW — arithmetic sum of 75 MW and 70 MW if the second building is delivered. It is not current campus capacity of any single defined basis.

25 MVA to 75 MVA — a municipal contextual description of the earlier change. [S12] It cannot be converted to MW without a disclosed power factor.

The MW/MVA inconsistency is not cosmetic. One municipal article refers to an increase from 25 MVA to 75 MVA, while Nebius and other records use MW. [S01][S02][S12] Apparent power in MVA cannot be substituted for real power in MW without a power-factor basis. The prior baseline should therefore remain unresolved rather than silently normalized.

The broader capacity language is also inconsistent. Contractor and company announcements tend to use the term without always specifying whether it means grid connection, facility design power or active compute load. [S01][S05] Nivos supplies the clearest basis for the existing number by calling 75 MW the enlarged connection. [S06] Nebius’s definitions reinforce why the categories must remain separate. [S08]

The physical-scope descriptions also differ. The municipal permit identifies one new data-centre building and a limited energy-transfer-building expansion, while Caverion describes two new data-centre buildings plus an existing-building extension. [S04][S05] Without approved phase drawings or an amended permit tying the descriptions together, the discrepancy should remain explicit rather than resolved by inference.

Project timeline

June 2024 — grid expansion contracted. Nivos and Global DC Oy sign the enlarged grid-connection agreement. [S03]

October 2024 — 75 MW expansion announced. Nebius publishes the capacity target; Nivos describes two new server halls. [S01][S03]

December 2024 — physical scope permitted. Mäntsälä approves the approximately 20,000 m² expansion. [S04]

January 2025 — ground works begin. [S06]

April–May 2025 — technical installation begins. Caverion’s delivery scope is publicly identified. [S05][S06]

November 2025 — first half enters use. [S06]

February 2026 — second half enters use. [S06]

March 2026 — 75 MW operational connection evidenced. Nebius says the expansion is complete; Nivos identifies the connection and commissioning sequence. [S06][S07]

October 2026 — second-building substation contracted. A separate 70 MW building is described, with substation delivery targeted for autumn 2027. [S10]

This history demonstrates why project state should be versioned rather than overwritten. The October 2024 claim became more credible through permit, construction and commissioning evidence. The October 2026 event did not replace the existing operational state; it added a separate future phase with a lower level of physical certainty.

Organizations and evidence roles

The evidence chain works because different organizations establish different parts of the project.

Nebius Group / Nebius DC Oy supplies operator claims, company reporting definitions and completion context. [S01][S07][S08][S13]

Nivos / Nivos Verkot supplies the local grid agreement, connection basis and commissioning sequence. [S03][S06]

Municipality of Mäntsälä supplies the formal permit and local project context. [S02][S04][S12]

Caverion supplies contract and technical-delivery evidence for both the completed expansion and future substation. [S05][S10]

Tekova identifies its delivery role and the approximate physical scale of the existing expansion. [S13]

No single source proves every element. Company announcements are best for what the company says it will do. The permit proves authorized scope. The utility record proves the connection context and reports commissioning. Contractor records prove contracted delivery scopes. The state assessment is strongest when those roles are not blurred.

What remains unknown

Several unknowns are decision-relevant rather than incidental.

First, the exact active IT load at the operating site is not disclosed in the reviewed record. A 75 MW connection describes the electrical boundary, not utilization. The approximately 40 MW liquid-cooling figure is attributed operator context, not a full utilization disclosure. [S06][S08]

Second, the public planning state of the second 70 MW building remains unresolved. The substation contract does not cite a building permit. The reviewed monitor did not locate a municipal decision, but that cannot establish absence. [S10][S11]

Third, construction and energization milestones for the new building remain unproven. Autumn 2027 is the contractor’s target for substation delivery. It should not be converted into a campus operation date.

Fourth, the capacity basis for the second 70 MW figure is not described with the same precision as Nivos’s existing 75 MW connection. Until a grid or operator record supplies a defined basis, the two figures should be shown separately before presenting any combined scenario.

Research conclusion and limitations

Mäntsälä is not simply a 145 MW project. It is an operational 75 MW-connected facility whose recent expansion can be traced through grid agreement, permit, construction and phased commissioning, plus a separate 70 MW building for which electrical infrastructure has now been contracted. [S03][S04][S06][S10]

That difference changes what a reader can responsibly conclude. The existing facility has crossed the physical thresholds that support an operational state. The second building has crossed a commercial-infrastructure threshold, but not the public-evidence thresholds for permitting, construction, energization or operation. The evidence supports monitoring the future phase; it does not support counting it as present capacity.

For DIS Atlas, this case is valuable because it makes the evidence model visible without exposing private scoring. Claims, permits, connection facts, commissioned state and known unknowns can coexist in one project record. The purpose is not to produce a larger number. It is to show which number describes which physical state—and what evidence would be needed for that state to change.

Limitations — this assessment uses public evidence available through 2 November 2026. It does not establish site-specific active IT load, second-building permitting, construction start, energization or a resolved MW/MVA conversion. The contractor and permit building-count descriptions also remain unreconciled.

Source roles

Original / primary evidence: S01–S08, S10, S12 and S13. These include company announcements, a municipal permit, utility records, a regulator-hosted filing and contractor records.

Secondary supporting sources: S09 and S11. They provide structured context and bounded evidence-gap checks; they do not control decisive permit, connection, commissioning or active-load conclusions.

Version
v1.0
Evidence cutoff
November 2, 2026

Limitations

  • Public records use MW, MVA and “capacity” on different bases; the evidence supports a 75 MW grid connection but does not reconcile those units or establish site-specific active IT load.

Known unknowns

  • The exact active IT load and current utilization of the 75 MW connection remain unknown; the permit, construction start and energization state of the separate 70 MW building are also unestablished.

Sources

01

Nebius Group · Published October 8, 2024 · Operator claim

Nebius to triple capacity at Finland data center to 75 MW

02

Municipality of Mäntsälä · Published January 22, 2025 · Secondary support

Mäntsälässä hyrrää pian yksi maailman tehokkaimmista datakeskuksista

03

Nivos · Published October 8, 2024 · Grid evidence

Nivos sopi sähköliittymän suurentamisesta Mäntsälän laajenevalle datakeskukselle

04

Municipality of Mäntsälä, Kuntakehityslautakunta · Published December 11, 2024 · Planning evidence

Rakennuslupa / Datakeskus / 505-407-3-286 / Moreenikatu 6

05

Assemblin Caverion Group / Caverion Finland · Published April 30, 2025 · Primary evidence

Caverion strengthens its position as key partner in major infrastructure investments in Europe

06

Nivos · Published March 31, 2026 · Grid evidence

Nebiuksen datakeskus laajeni vauhdilla – Nivos vastasi ketterästi sähkönsiirron tarpeisiin

07

Nebius Group · Published March 31, 2026 · Operator claim

Nebius to construct 310 MW AI factory in Finland

08

Nebius Group N.V. / U.S. Securities and Exchange Commission · Published April 30, 2026 · Company filing

Nebius Group N.V. Annual Report on Form 20-F for year ended 31 December 2025

09

Datakeskushankkeiden kansallinen rekisteri · Accessed November 2, 2026 · Secondary support

Nebius, Mäntsälä — Datakeskushankkeiden kansallinen rekisteri

10

Assemblin Caverion Group / Caverion Finland · Published October 2, 2026 · Primary evidence

Caverion Finland will deliver a EUR 15 million substation for AI cloud company Nebius

11

Kuntamonitori · Accessed November 2, 2026 · Context only

Nebius Mäntsälä 2, Kapuli

12

Municipality of Mäntsälä · Published December 17, 2024 · Context only

Datakeskustoimija Verne alkaa rakentaa uutta datakeskuskampusta Mäntsälään

13

Tekova · Accessed November 2, 2026 · Primary evidence

Data centre, Mäntsälä

Continue the system

Related intelligence.

Signal · 2026-11-02 00:00

Nebius contracts substation for a second 70 MW Mäntsälä building

AI Infrastructure · 3 min

Signal · 2026-06-25

AI Chip Manufacturing Faces Supply Constraints Amid Export Controls in Semiconductor Industry

AI Infrastructure · 2 min

Signal · 2026-06-20

AI Infrastructure CapEx Surge Indicates Hyperscaler AI Compute Acceleration

AI Infrastructure · 2 min
Research contextKeep this research system in view.

Related research and future publications remain available on the site.

Email updates are currently unavailable.

Research and Briefs remain available on this site.

DOBERMANX

Independent Research & Intelligence.

WorkResearchBriefsDIS AtlasAbout
ConnectLinkedIn ↗Professional networkX ↗@dobermanxdataYouTube ↗Research & videoEmail ↗dobermanvc@gmail.com
StandardsMethodologyDisclosurePrivacyCookiesTerms

© 2025–2026 DOBERMAN X. Research and information only. Not investment advice.